Friday, 10 January 2014

A SAMPLE OF A PROJECT PROPOSAL FOR ACADEMIC PURPOSES


A SAMPLE OF A PROJECT PROPOSAL FOR ACADEMIC PURPOSES

PROJECT PROPOSAL
CONSTRUCTION OF A RECORDS STORAGE FACILITY IN 

HOIMA REGIONAL REFERRAL HOSPITAL
BY
STUDENT NAME: KATUGUME SUNNY
PROJECT DIRECTOR: HOSPITAL ADMINISTRATOR
FROM 5TH JULY 2014-5TH JULY 2015

PROJECT SUMMARY: The project of constructing a records storage facility in Hoima Regional hospital will take a period of one year. By the time the project is completed, it will help the information users to easily access records needed at a particular time. The project will be undertaken due to the many challenges which the records department has been facing for instance poor records storage and retrieval partially due to shortage of a designated place for records.  The records storage facility will have four main floors including the one for a records center for current records, a registry holding records in a semi current stage waiting for disposition or archival and an archive for records of permanent value.


THE ORGANIZATIONAL HISTORY
 HISTORICAL BACKGROUND OF THE HOSPITAL:
The hospital was established in 1910 as Hoima hospital under the ministry of health. In 1998 it became a referral hospital for Hoima district where other health centers in the district could refer their patients. In 2002 it became a regional referral hospital covering areas of Masindi, Hoima, Kibale, kiryandongo, kiboga and Buliisa. Therefore all health centers in the districts mentioned refer their patients to Hoima regional referral hospital up for further treatment. The hospital still operates as a regional referral hospital up to present day.

  MISSION:
To provide specialized and limited general curative, preventive, health pro motive and rehabilitative health services to Bunyoro kitara region for improved quality of life.

VISION:
 To become a center of excellence for provision of high quality general and specialized health services for a healthy and productive population in Bunyoro kitara region.

THE BACKGROUND AND ANALYSIS OF THE PROBLEM TO BE ADDRESSED
How far has Hoima Regional Referral Hospital been effective in records management? Hoima Regional Referral Hospital being one of the referral hospitals in Uganda, it generates a lot of health services to the population of Uganda. This means that, the hospital generates, receives and maintains volumes of both medical records and non medical records which need proper care to provide continued access to such records. However, the hospital faces a lot of challenges in records management. For example not enough funds from the government to even support the records department, lack of enough storage space for records, embezzlement of funds meant for supporting records management, poor records disposition policy and so many challenges. Therefore there is need for the establishment of a records storage facility which will help in curbing such challenges and hence good records management system at the hospital.


THE PROJECT GOAL
To construct the best records storage facility for Hoima Regional Referral Hospital

PROJECT OBJECTIVES
To ease records storage and retrieval in time
To help in determining the records retention and disposition policy
 To curb the challenges facing the records department
To enhance a proper classification and filing system

PROJECT IMPLEMENTATION PLAN
The project will be implemented by considering the project plan. Actually project implementation will be done by starting on the actual construction of the records storage facility. This will be started on 5th July 2014 and it should be completed on 5th July 2o15, a period of only one year. This will be done by executing all the project activities to produce the project deliverables, the project activities will include,
·         Planning for the project
·         Identifying and surveying the land
·         Clearing the land and delivery of the building materials
·         Actual building of the facility
·         Installation of equipments
·         Monitoring and evaluation
·         Formal handover


THE ANNUAL PROJECT BUDGET
BUDGET OUTLINE
AMOUNT
GOVERNMENT FUND
Ugandan shillings(ug shs)
OTHER SOURCES OF FUND
Project personnel



Consultant 1
1000000
1000000

Builders 10
2000000
2000000

Administrative support



Official travel to in two districts
1month*100000
   100000

Component total

3100000

Equipments



Buying the land

5000000

Construction materials like bricks, sand, cement, trees

700000

Bulbs  and water pipes

6000000

Component total

11700000
Engender health community
Miscellaneous



Sundry and communications

100000

Inflation on items

200000

Component total

300000





Grand total

15100000















No comments: